Which of the following is MOST likely to be the first document created by the project manager?
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
A . Project charter
B . Project management plan
C . Project statement of work
D . Project schedule
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299