Which of the following is MOST likely the reason for this?
A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a project manager and refers to another department within the company .
Which of the following is MOST likely the reason for this?
A . There are not enough project managers available for additional work
B . The work does not align with the strategic objectives of the organization
C . This is ongoing work the vendor has been hired to perform
D . The third party has a reputation for expertise in this area
Answer: D