Which of the following is MOST likely the reason for this?

A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a project manager and refers to another department within the company .

Which of the following is MOST likely the reason for this?
A . There are not enough project managers available for additional work
B . The work does not align with the strategic objectives of the organization
C . This is ongoing work the vendor has been hired to perform
D . The third party has a reputation for expertise in this area

Answer: D

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments