Which of the following is less likely to be included in the change control sub-phase of the maintenance phase of a software product?
A . Estimating the cost of the changes requested
B . Recreating and analyzing the problem
C . Determining the interface that is presented to the user
D . Establishing the priorities of requests
Answer: D
Explanation: Change control sub-phase includes Recreating and analyzing the problem, Determining the interface that is presented to the user, and Establishing the priorities of requests. Source: KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide: Mastering the Ten
Domains of Computer Security, John Wiley & Sons, 2001, Chapter 7: Applications and Systems Development (page 252).