Which of the following is False?
A Successful project management team should.
A . Have business, user and supplier stakeholder representation
B . Never be reviewed as members should stay with the team for the duration
C . Ensure appropriate governance by defining responsibilities for directing, managing and delivering the project and clearly defining accountability at all levels
D . Have an effective strategy to manage communication flows to and from stakeholders
Answer: B