Which of the following is categorised as fixed cost?
A . Additional pallet hires due to higher demand in year-end season
B . Land rental paid in advance
C . Governments taxes
D . Raw materials for next year production
Answer: B
Explanation:
Anorganisation’s expense can be categorised into three groups:
Fixed Costs C costs that do not change with output.
Variable Costs C costs that vary in direct proportion to output.
Semi-variable costs C costs that are a combination of the above, with both a fixed and
variable element.
Among the four options:
"Land rental paid in advance": This is fixed cost. The rental won’t increase when the production increases.
"Additional pallet hires due to higher demand in year-end season": This can be identified as semi-variable cost (or step cost).
"Governments taxes": The taxes are often levied by a percentage of income or revenue. Therefore, it is variable
"Raw materials for next year production": This is obviously variable cost.
Reference:
CIPS study guide page 79-84
Study tips: Fixed variable and semi-variable costs – AAT Comment
Latest L4M5 Dumps Valid Version with 162 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund