Which of the following is BEST to use to document the effects of this delay?

A hurricane delays the shipment of critical equipment for a project.

Which of the following is BEST to use to document the effects of this delay?
A . Issue log
B . Gantt chart
C . Milestone chart
D . Change control log

Answer: D

Explanation:

The project manager should use a change control log to document the effects of the hurricane delay on the project. A change control log is a tool that records and tracks any changes that occur during the project lifecycle. It usually includes information such as change ID, description, impact, status, approval, and resolution. A change control log can help to monitor and manage the changes that affect the project scope, schedule, cost, quality, or resources and ensure that they are aligned with the project objectives and stakeholder expectations.

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments