Which of the following is an output of the Identify Stakeholders process?

Which of the following is an output of the Identify Stakeholders process?
A . Scope baseline
B . Project charter
C . Stakeholder register
D . Project scope statement

Answer: C

Explanation:

The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success. Stakeholder register and stakeholder management strategy are outputs of this process.

Answer. B is incorrect. Project charter is one of the inputs of the Identify Stakeholders process.

Answer. A is incorrect. Scope baseline is one of the outputs of the Create Work Breakdown Structure (WBS) process.

Answer. D is incorrect. Project scope statement is one of the outputs of the Define Scope process.