Which of the following is an output of the Define Activities process?

Which of the following is an output of the Define Activities process?
A . Activity list
B . Project plan
C . Activity duration estimates
D . Project schedule

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments