Which of the following is an important part of the change request process for which the administrator still must plan?
A network administrator wants to plan a major OS upgrade of the router, which acts as a default gateway in an organization. The administrator has documented the purpose of the change, scoped the change, and completed a comprehensive risk analysis.
Which of the following is an important part of the change request process for which the administrator still must plan?
A . Inform management regarding the anticipated amount of downtime
B . Document a backout plan to roll back changes to the router
C . Configure a redundant data path to eliminate downtime
D . Make the downtime window larger than actually anticipated
Answer: B
Latest 220-1002 Dumps Valid Version with 623 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments