Which of the following is an example of the test closure activity indicated as "lessons learned"?
K2 1 credit
A . Archive all the test results of the acceptance testing phase
B . Deliver a list of the open defects of a software product released into production to the service desk team
C . Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
D . Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing
Answer: C