Which of the following is an activity that should trigger a review of the CSMS?
Which of the following is an activity that should trigger a review of the CSMS?
Available Choices (select all choices that are correct)
A . Budgeting
B. New technical controls
C. Organizational restructuring
D. Security incident exposing previously unknown risk.
Answer: D