Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
A . Evaluating the project
B . Releasing the resources
C . Closing the contracts
D . Reconciling the budget

Answer: A

Explanation:

Evaluating the project is an activity that should be used in the closing phase of a project to support the project triple constraint. This involves reviewing the project plan, deliverables, and outcomes to ensure they meet the project objectives and requirements.

Reference: CompTIA Project+ Study Guide Section 4.4.4