Which of the following is addressed within the Needs Analysis part of the AV Design process?
Which of the following is addressed within the Needs Analysis part of the AV Design process?
A . creating the project timeline
B . outlining project Bill of Materials
C . identifying key stakeholders for the project
D . identifying functional requirements of the project
Answer: D
Explanation:
The Needs Analysis phase of the AV Design process focuses on understanding the specific needs and requirements of the project. This includes identifying the functional requirements, which detail what the system must be able to do to meet the client’s objectives. This step ensures that the design will align with the user’s needs and provides a foundation for developing the technical specifications and design plans.