Which of the following is a schedule that illustrates the duration of an activity?

Which of the following is a schedule that illustrates the duration of an activity?
A . Process diagram
B . Ishikawa diagram
C . Gantt chart
D . Pareto chart

Answer: C

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168