Exam4Training

Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?

Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?
A . Eliminating all changes that may affect the quality of deliverables and processes
B. Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization by the Product Owner.
C. Providing requests for changes in a project.
D. Approving changes that are amended, removed, or added according to project requirements, and communicating the same to the Scrum Team.

Answer: B

Latest ASM Dumps Valid Version with 39 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version