CORRECT TEXT
Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?
A . Monte Carlo Analysis.
B . Project Management Information System (PMIS).
C . Earned Value Management (EVM).
D . Integrated Project Plan
Answer: A
Latest IIA-CIA-Part3 Dumps Valid Version with 402 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund