Which of the following is a process in the initiate phase of Scrum?

Which of the following is a process in the initiate phase of Scrum?
A . Identify Scrum Master and Stakeholder(s)
B . Estimate User Stories
C . Conduct Daily Standup
D . Commit User Stories

Answer: A

Explanation:

Reference: https://www.scrumstudy.com/whyscrum/scrum-initiate