Which of the following is a part of change control?
Which of the following is a part of change control?
A . Requests for change are realised.
B . Requests for change are mitigated.
C . Requests for change are evaluated.
D . Requests for change are resolved.
Answer: C
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments