Which of the following is a key step in preparing for a recovery with PowerProtect Data Manager (PPDM)?

Which of the following is a key step in preparing for a recovery with PowerProtect Data Manager (PPDM)?
A . Setting up a direct link to external cloud storage
B . Regularly updating the disaster recovery plan documentation
C . Configuring the recovery point objectives (RPOs) and recovery time objectives (RTOs)
D . Assigning a dedicated team for manual recovery operations

Answer: C