You are an experienced Project Manager that has been entrusted with a project to develop a machine which produces auto components. You have scheduled meetings with the project team and the key stakeholders to identify the risks for your project.
Which of the following is a key output of this process?
A . Risk Register
B . Risk Management Plan
C . Risk Breakdown Structure
D . Risk Categories
Answer: A
Explanation:
The primary outputs from Identify Risks are the initial entries into the risk register. The risk register ultimately contains the outcomes of other risk management processes as they are conducted, resulting in an increase in the level and type of information contained in the risk register over time.
Incorrect Answers:
B, C, D: All these are outputs from the "Plan Risk Management" process, which happens prior to the starting of risk identification.
Latest CRISC Dumps Valid Version with 933 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund