Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles?
A . Linear project life cycles set the deployment baseline for the whole project.
B . In an iterative project life cycle the scope and quality are fixed in the deployment baseline.
C . Only deployment baselines in iterative life cycles have an integrated baseline review.
D . Only deployment baselines in linear life cycles have an integrated baseline review
Answer: A