A chief audit executive wants to implement an enterprisewide resource planning software.
Which of the following internal audit assessments could provide overall assurance on the likelihood of the software implementation’s success?
A . Readiness assessment.
B . Project risk assessment.
C . Post-implementation review.
D . Key phase review.
Answer: A