Exam4Training

Which of the following infotypes should you configure?

You want to activate activity allocations for time-related data, while disabling cost assignment.

Which of the following infotypes should you configure? Please choose the correct answer.
A . IT2004 (Availability)
B . IT2011 (Time Events)
C . IT2001 (Absences)
D . IT2005 (Overtime)

Answer: C

Exit mobile version