Which of the following information system auditors’ recommendations best ensures that the control weaknesses found during the audit process are properly mitigated?
A . Report progress to the Audit Committee.
B . Implement the software system and enter the Information Systems Auditor Action Plan.
C . Assign tasks to followers and follow up.
D . Perform a cost-benefit analysis to the rectification strategy.
Answer: C