Which of the following information should the project manager provide?

The executive sponsor asks a project manager to summarize the following for a project:

Final capital expenditures.

Anticipated cost of new employee resources to support the solution.

Maintenance estimates.

Which of the following information should the project manager provide?
A . Cost baseline
B . Burn rate
C . Cost variance report
D . Total project cost

Answer: A