Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
A . Sales clerk
B . Marketing representative
C . Team lead
D . Product item

Answer: B