Which of the following events would MOST likely have triggered the meeting?

A meeting has taken place with quality assurance tram members and the project manager.

Which of the following events would MOST likely have triggered the meeting?
A . Audit
B . Risk register update
C . Task completion
D . Resource change

Answer: A