Which of the following events does NOT help the Scrum Team in identifying or resolving risks?
A . Daily Standup Meeting
B . Sprint Planning Meeting
C . Financial Planning Meeting
D . Prioritized Product Backlog Review Meeting
Answer: D
Explanation:
Reference: http://blog.scrumstudy.com/risk-management-in-scrum/