Which of the following elements of planning gap measures the gap between the total potential for the market and the actual current usage by all the consumers in the market?

Which of the following elements of planning gap measures the gap between the total potential for the market and the actual current usage by all the consumers in the market?
A . Project gap
B . Product gap
C . Competitive gap
D . Usage gap

Answer: D