Which of the following elements can be generated by material requirements planning (MRP)? There are 3 correct answers to this question.
Which of the following elements can be generated by material requirements planning (MRP)? There are 3 correct answers to this question.
A . Production order
B . Purchase requisition
C . Delivery schedule line
D . Planned order O Purchase order
Answer: B,C,D
Latest C_TS452_1909 Dumps Valid Version with 90 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments