Which of the following elements are used during forward scheduling in material requirements planning? Note: There are 2 correct Answers to this question.

Which of the following elements are used during forward scheduling in material requirements planning? Note: There are 2 correct Answers to this question.
A . Purchasing processing time
B . Total replenishment lead time
C . Goods receipt processing time
D . Shipping processing time

Answer: A, C