Which of the following DR testing scenarios is described as verbally walking through each step of the DR plan in the context of a meeting?

Which of the following DR testing scenarios is described as verbally walking through each step of the DR plan in the context of a meeting?
A . Live failover
B . Simulated failover
C . Asynchronous
D . Tabletop

Answer: D

Explanation:

The DR testing scenario that is described as verbally walking through each step of the DR plan in the context of a meeting is tabletop. A tabletop test is a type of disaster recovery (DR) test that involves discussing and reviewing the DR plan with key stakeholders and participants in a simulated scenario. A tabletop test does not involve any actual execution of the DR plan or any disruption of the normal operations. A tabletop test can help identify gaps, issues, or inconsistencies in the DR plan and improve communication and coordination among the DR team members.

Latest SK0-005 Dumps Valid Version with 90 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments