Which of the following documents would contain these items?

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.

Which of the following documents would contain these items?
A . Business case
B . Requirements document
C . Project timeline
D . Task plan

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138