The management team needs to ensure unnecessary modifications to the corporate network are not permitted and version control is maintained.
Which of the following documents would BEST support this?
A . An incident response plan
B. A business continuity plan
C. A change management policy
D. An acceptable use policy
Answer: C
Explanation:
A change management policy is a document that outlines the procedures and guidelines for making changes to a network or system, including how changes are approved, tested, and implemented. By following a change management policy, organizations can ensure that unnecessary modifications to the network are not permitted and version control is maintained.
Latest N10-008 Dumps Valid Version with 132 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund