The management team needs to ensure unnecessary modifications to the corporate network are not permitted and version control is maintained.
Which of the following documents would BEST support this?
A . An incident response plan
B . A business continuity plan
C . A change management policy
D . An acceptable use policy
Answer: C
Explanation:
A change management policy is a document that outlines the procedures and guidelines for making changes to a network or system, including how changes are approved, tested, and implemented. By following a change management policy, organizations can ensure that unnecessary modifications to the network are not permitted and version control is maintained.
Reference: Network+ N10-008 Objectives: 1.6 Given a scenario, implement network configuration and change management best practices.