Which of the following documents will the company MOST likely release FIRST?
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?
A . RFO
B . RFI
C . RFP
D . RFQ
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300