Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?

A project manager must create documentation before the project kickoff meeting .

Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?
A . Responsibility matrix
B . Resource allocation plan
C . Project charter
D . Statement of work

Answer: C