Which of the following documents should the project team reference to fast-track the project?

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.

Which of the following documents should the project team reference to fast-track the project? (Choose two.)
A . Scope management plan
B . Configuration management plan
C . Network diagram
D . Project schedule
E . Project plan

Answer: C,D

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 171