During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system.
Which of the following documents should the project manager use to identify who requested this item?
A . Issue log
B . Risk register
C . Defect log
D . Traceability matrix
Answer: D
Explanation:
A traceability matrix is a document that maps the requirements of a project to the deliverables, test cases, and changes that are produced to meet those requirements. It helps the project manager to track the origin, status, and impact of each requirement throughout the project life cycle. A traceability matrix can also identify who requested or approved each requirement. Therefore, the project manager can use the traceability matrix to identify who requested the specific item that caused the regression test to fail12.
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund