Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP.
Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
A . Milestone chart
B. Work breakdown structure
C. Project charter
D. Detailed scope statement
Answer: C
Explanation:
The project manager should produce a project charter first to start communication about the boundaries of the project. A project charter is a document that formally authorizes a project and defines its high-level scope, objectives, assumptions, constraints, stakeholders, roles and responsibilities, and key deliverables. A project charter can help to communicate the project vision and expectations to all stakeholders and provide a basis for future project decisions23