Exam4Training

Which of the following documents should the project manager expedite first?

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product.

Which of the following documents should the project manager expedite first?
A . RFI
B . RFP
C . RFQ
D . RFB

Answer: B

Explanation:

When a project team lacks hands-on experience and decides to involve a third-party vendor for product development, the first document to expedite is a Request for Proposal (RFP). An RFP outlines the project requirements and asks potential vendors to submit proposals detailing how they would meet those requirements and at what cost. This allows the project manager to evaluate the capabilities and offerings of different vendors before making a decision.

Reference = CompTIA Project+ Certification Study Guide (PK0-005)

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version