Which of the following documents should the project manager consult?

A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to escalate the issue .

Which of the following documents should the project manager consult?
A . Issue log
B . RACI chart
C . Risk management plan
D . Organizational chart

Answer: B