Which of the following documents should the project manager address FIRST?

A new stakeholder has requested the status and progress reports for the project milestones .

Which of the following documents should the project manager address FIRST?
A . Project communication plan
B . Project status report
C . Project management plan
D . Project backlog

Answer: C