Which of the following documents sets the project objectives?

Which of the following documents sets the project objectives?
A . Project charter
B . Project schedule
C . Project scope statement
D . Project organization chart

Answer: C

Latest PgMP Dumps Valid Version with 452 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments