Which of the following documents need to be updated as events occur during a project? (Select TWO).
Which of the following documents need to be updated as events occur during a project? (Select TWO).
A . Change request
B . Risk register
C . Meeting minutes
D . Issue log
E . Status report
Answer: C,E