Which of the following documents is the best source for the PM to use to confirm this assertion?

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase.

Which of the following documents is the best source for the PM to use to confirm this assertion?
A . Issue log
B . Scope statement
C . Risk report
D . Change log

Answer: D

Explanation:

A change log is a document that records and tracks the changes that are made to the project scope, schedule, budget, or quality. It helps the project manager to monitor and control the project performance and ensure that the changes are aligned with the project objectives and stakeholders’ expectations. A change log can also include information such as the change description, impact, status, approval, and date. A change log is the best source for the PM to use to confirm the assertion that the functionality request was rejected during the planning phase, as it would show the details and reasons for the rejection12.

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments