Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?
A . SOW
B . PO
C . SLA
D . MOU

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299