Which of the following documents can the sponsor review to determine the project’s performance?

Despite receiving regular updates, a sponsor learns a project recently slipped.

Which of the following documents can the sponsor review to determine the project’s performance? (Select two.)
A . Status report
B . Communication plan
C . Issue log
D . Project schedule
E . Action items list
F . Risk register

Answer: A,C