Which of the following disaster recovery tests includes the operations that shut down at the primary site, and are shifted to the recovery site according to the disaster recovery plan?

Which of the following disaster recovery tests includes the operations that shut down at the primary site, and are shifted to the recovery site according to the disaster recovery plan?
A . Structured walk-through test
B . Simulation test
C . Full-interruption test
D . Parallel test

Answer: C