Which of the following describes these types of activities?
When creating a project schedule, a project manager adds activities with zero duration.
Which of the following describes these types of activities?
A . Critical paths
B . Resources
C . Milestones
D . Work breakdown structures
Answer: C
Explanation:
Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments